Godrej Neopolis Completion Date


Featured Image of Godrej Neopolis Completion Date

The Godrej Neopolis Completion Date is 1 November 2028 (four years from the initial launch). The completion date marks when the project is built fully and ready for use, and it is clearly stated in the contracts.

The completion date is the anticipated finish of construction activities for a property. It signifies when the building is ready for occupancy. On this date, the property will pass through all inspections.

Godrej Properties has a record of delivering all their projects on time. They have handed 30+ projects on time across major cities in India. Godrej Neopolis will be launched in October 2024 after receiving all needed approval. The project construction is separated into small schedules to complete it at the correct time on the specified completion date.

The completion of the project plan is as follows,

Substructure

Project Work Estimated From Date Estimated To Date
Earthwork and other leveling work 01-12-2024 01-04-2025
Foundation footing work 01-04-2025 01-06-2025
Upto Plinth Level 15-06-2025 16-10-2025
Substructure flooring (Parking Floor, more than one floor below general ground level) 20-08-2025 18-11-2025
Wall (All types) 15-06-2025 16-09-2025

Super-Structure

Project Work Estimated From Date Estimated To Date
RCC or MS Framed structure 20-06-2025 20-08-2026
Masonry Work 19-08-2025 18-12-2026
Plastering inside, outside & Ceiling 09-09-2025 18-03-2026
Doors, Windows, etc 09-10-2025 28-11-2026
Basic work of Water supply, Sanitary 03-09-2025 02-05-2026
Flooring, Tiles work (All types) 24-10-2025 14-09-2026
Railing and Grill fixing 18-09-2025 18-11-2026

Finishing Works

Project Work Estimated From Date Estimated To Date
Electrical, Water supply and Sanitary Finish 31-07-2027 14-09-2028
Painting 09-10-2027 29-10-2028
Fire prevention and firefighting fitting 31-07-2027 14-09-2028
Weatherproof work (tile, concrete) 18-11-2027 17-04-2028
Elevation work 18-12-2027 29-09-2028
Internal and External work 18-12-2027 01-11-2028

The date of completion holds a lot of importance for the buyers. Buyers can physically see the spaces of their homes. When the project is finished, all its features will be available and are then operational. All the services are open for people to use. The clubhouses, swimming pools, parks, and other spaces are functional.

The project will be completed on time that is set for the completion of the project. It also marks Godrej Properties commitment to deliver the best houses in the promised time. Buyers are eagerly waiting for the specified completion date from now as they can start living in their dream houses soon.

Featured Image of Godrej Neopolis Address
Featured Image of Godrej Neopolis FAQs
Featured Image of Godrej Neopolis Distance

Featured Image of About Godrej Properties
Featured Image of About Kokapet
Featured Image of Godrej Neopolis Connectivity

Featured Image of Godrej Neopolis Map
Featured Image of Godrej Neopolis Offers
Featured Image of Godrej Neopolis Office

Disclaimer : The content is for information purposes only and does not constitute an offer to avail of any service. Prices mentioned are subject to change without notice and properties mentioned are subject to availability. Images for representation purposes only. This is the official website of authorized marketing partner. We may share data with RERA registered brokers/companies for further processing. We may also send updates to the mobile number/email id registered with us. All Rights Reserved.

Enquiry
Enquire Now